Downtown Tunnel Reconstruction Update

LebAlert , Tunnel

  • Sent 09/16/2020 14:09 EDT
  • Translated: Arabic

ED Swett has completed construction of the tunnel roof concrete slabs on the western and central sections of the Tunnel. As such, pedestrian access to the Mall from the west end is being re-established this week. The next phase of construction includes removal and reconstruction of the eastern tunnel concrete slabs, as well as partial parking lot reconstruction on the west end of the tunnel. This western edge parking lot is scheduled to be reopened in mid-October for public use. Portions of this parking lot may be cordoned off on occasion to allow for finish work and/or construction vehicle access. Eastern slab reconstruction is expected to be completed in December, with final hardscape and landscape items completed in the spring of 2021. If you have any questions please contact Brian Vincent, PE at bvincent@lebanonnh.gov or (603) 448-3112. Thank you for your continued patience and understanding as this project proceeds.